utf8proj Diagnostic Specifications

This document specifies the diagnostic messages emitted by utf8proj during scheduling and analysis. These diagnostics are the user-facing contract — implementations must use these exact messages.

Design Principles

  1. Actionable: Every diagnostic suggests what to do
  2. Contextual: Messages include task/resource identifiers
  3. Graduated: Severity reflects actual risk, not pedantry
  4. Machine-readable: Codes are stable for tooling integration

Severity Levels

Level Code Prefix Meaning --strict Behavior
Error E, C001-C009 Cannot proceed Always fatal
Warning W, C010-C019 Likely problem Becomes error
Hint H, C020-C029 Suggestion Becomes warning
Info I Informational Unchanged

Emission Ordering

For determinism and testability, diagnostics are emitted in this order:

  1. Structural errors (E001, E002, E003) - fatal issues first
  2. Calendar errors (C001, C002) - configuration issues
  3. Cost-related warnings (W002, W004) - budget risk
  4. Assignment-related warnings (W001, W003) - planning gaps
  5. Calendar warnings (C010, C011) - scheduling conflicts
  6. MS Project compatibility warnings (W014) - migration issues
  7. Hints (H001, H002, H003, H004) - suggestions
  8. Calendar hints (C020, C022, C023) - calendar suggestions
  9. Info (I001, I002, I003, I004, I005) - summary last

Within each category, diagnostics are ordered by source location (file, line, column).

This ordering ensures:

  • Users see blocking issues immediately
  • CI logs are diffable
  • LSP clients receive stable sequences

Diagnostic Catalog


W001: Abstract Assignment

Severity: Warning

Trigger: Task is assigned to a resource_profile (abstract) rather than a concrete resource.

Condition:

task.assignments.any(a => project.profiles.contains(a.resource_id))

Message Template:

warning[W001]: task '{task_id}' is assigned to abstract profile '{profile_id}'
  --> {file}:{line}
   |
   | assign: {profile_id}
   |         ^^^^^^^^^^^^ abstract profile, not a concrete resource
   |
   = note: cost range is ${min} - ${max} ({spread}% spread)
   = hint: assign a concrete resource to lock in exact cost

Example:

warning[W001]: task 'api_development' is assigned to abstract profile 'backend_developer'
  --> crm_migration.proj:45
   |
   | assign: backend_developer
   |         ^^^^^^^^^^^^^^^^^ abstract profile, not a concrete resource
   |
   = note: cost range is $4,000 - $8,000 (100% spread)
   = hint: assign a concrete resource to lock in exact cost

Rationale: Abstract assignments are valid but represent planning uncertainty. Users should be aware when their schedule contains unresolved abstractions.


W002: Wide Cost Range

Severity: Warning

Trigger: A task's cost range spread exceeds threshold (default: 50%).

Condition:

let spread = (cost_range.max - cost_range.min) / cost_range.expected * 100;
spread > threshold

Message Template:

warning[W002]: task '{task_id}' has wide cost uncertainty ({spread}% spread)
  --> {file}:{line}
   |
   = cost range: ${min} - ${max} (expected: ${expected})
   = contributors:
       - {profile_id}: ${profile_min} - ${profile_max}
       - {trait_id} multiplier: {multiplier}x
   |
   = hint: narrow the profile rate range or assign concrete resources

Example:

warning[W002]: task 'data_migration' has wide cost uncertainty (120% spread)
  --> crm_migration.proj:67
   |
   = cost range: $12,000 - $26,400 (expected: $19,200)
   = contributors:
       - senior_developer: $150 - $250/day
       - contractor trait: 1.2x multiplier
   |
   = hint: narrow the profile rate range or assign concrete resources

Configuration:

--cost-spread-threshold=50  # percentage, default 50

W003: Unknown Trait

Severity: Warning

Trigger: A profile references a trait that is not defined.

Condition:

profile.traits.any(t => !project.traits.contains(t))

Message Template:

warning[W003]: profile '{profile_id}' references unknown trait '{trait_id}'
  --> {file}:{line}
   |
   | traits: {trait_id}
   |         ^^^^^^^^^ not defined
   |
   = note: unknown traits are ignored (multiplier = 1.0)
   = hint: define the trait or remove the reference

Example:

warning[W003]: profile 'senior_developer' references unknown trait 'onsite'
  --> crm_migration.proj:12
   |
   | traits: senior, onsite
   |                 ^^^^^^ not defined
   |
   = note: unknown traits are ignored (multiplier = 1.0)
   = hint: define the trait or remove the reference

W004: Approximate Leveling

Severity: Warning

Trigger: Resource leveling was applied but could not fully resolve all conflicts.

Condition:

leveling_result.unresolved_conflicts.len() > 0

Message Template:

warning[W004]: resource leveling incomplete - {count} conflict(s) unresolved
   |
   = unresolved:
       - {resource_id} over-allocated on {date_range} ({usage}% vs {capacity}% capacity)
   |
   = note: project extended by {days} day(s) to {new_end}
   = hint: add resources, extend deadlines, or reduce scope

Example:

warning[W004]: resource leveling incomplete - 2 conflict(s) unresolved
   |
   = unresolved:
       - alice over-allocated on 2025-03-10..2025-03-14 (150% vs 100% capacity)
       - bob over-allocated on 2025-03-12 (200% vs 100% capacity)
   |
   = note: project extended by 5 day(s) to 2025-04-15
   = hint: add resources, extend deadlines, or reduce scope

W014: Container Dependency Without Child Dependencies

Severity: Warning

Trigger: A container task has dependencies, but one or more of its children do not depend on any of the container's predecessors.

Condition:

container.depends.is_not_empty()
  && child.depends.intersection(container.depends).is_empty()

Message Template:

warning[W014]: container '{container_name}' depends on [{deps}] but child '{child_name}' has no matching dependencies
  --> {file}:{line}
   |
   = MS Project behavior: '{child_name}' would be blocked until [{deps}] completes
   = utf8proj behavior: '{child_name}' can start immediately (explicit dependencies only)
   = hint: add 'depends: {first_dep}' to match MS Project behavior

Example:

warning[W014]: container 'Development Phase' depends on [design_approval] but child 'Feature X' has no matching dependencies
  --> project.proj:45
   |
   = MS Project behavior: 'Feature X' would be blocked until [design_approval] completes
   = utf8proj behavior: 'Feature X' can start immediately (explicit dependencies only)
   = hint: add 'depends: design_approval' to match MS Project behavior

Rationale: MS Project implicitly propagates container dependencies to children. utf8proj requires explicit dependencies. This warning helps users migrating from MS Project understand when their schedule will behave differently, and suggests how to match MS Project semantics if desired.

Related: See docs/DESIGN_PHILOSOPHY.md and docs/rfcs/RFC003_CONTAINER_DEPENDENCY_SEMANTICS.md for the design rationale.

Auto-Fix: Use utf8proj fix container-deps to automatically propagate container dependencies to children:

# Preview changes (output to stdout)
utf8proj fix container-deps project.proj

# Write to a new file
utf8proj fix container-deps project.proj -o project_fixed.proj

# Modify in place (use with caution)
utf8proj fix container-deps project.proj --in-place

H001: Mixed Abstraction Level

Severity: Hint

Trigger: A task has assignments at different abstraction levels (both concrete and abstract).

Condition:

task.assignments.any(is_concrete) && task.assignments.any(is_abstract)

Message Template:

hint[H001]: task '{task_id}' mixes concrete and abstract assignments
  --> {file}:{line}
   |
   | assign: {resource_id}, {profile_id}
   |         ^^^^^^^^^^^^   ^^^^^^^^^^
   |         concrete       abstract
   |
   = note: this is valid but may indicate incomplete refinement
   = hint: consider refining '{profile_id}' to a concrete resource

Example:

hint[H001]: task 'integration_testing' mixes concrete and abstract assignments
  --> crm_migration.proj:89
   |
   | assign: alice, qa_engineer
   |         ^^^^^  ^^^^^^^^^^^
   |         concrete  abstract
   |
   = note: this is valid but may indicate incomplete refinement
   = hint: consider refining 'qa_engineer' to a concrete resource

H002: Unused Profile

Severity: Hint

Trigger: A resource_profile is defined but never assigned to any task.

Condition:

!project.tasks.flatten().any(t => t.assignments.contains(profile.id))

Message Template:

hint[H002]: profile '{profile_id}' is defined but never assigned
  --> {file}:{line}
   |
   | resource_profile {profile_id} "{name}" { ... }
   | ^^^^^^^^^^^^^^^^ unused
   |
   = hint: assign to tasks or remove if no longer needed

H003: Unused Trait

Severity: Hint

Trigger: A trait is defined but not referenced by any profile.

Condition:

!project.profiles.any(p => p.traits.contains(trait.id))

Message Template:

hint[H003]: trait '{trait_id}' is defined but never referenced
  --> {file}:{line}
   |
   | trait {trait_id} { ... }
   | ^^^^^ unused
   |
   = hint: add to profile traits or remove if no longer needed

H004: Task Without Scheduling Constraint

Severity: Hint

Trigger: A leaf task has no predecessors and no date constraints (dangling/orphan task in CPM network).

Condition:

task.children.is_empty()  // leaf task only
  && task.depends.is_empty()  // no predecessors
  && task.constraints.is_empty()  // no date constraints

Message Template:

hint[H004]: task '{task_name}' has no predecessors or date constraints
  --> {file}
   |
   = '{task_name}' will start on project start date (ASAP scheduling)
   = hint: add 'depends:' or 'start_no_earlier_than:' to anchor scheduling logic

Example:

hint[H004]: task 'Data Migration' has no predecessors or date constraints
  --> project.proj
   |
   = 'Data Migration' will start on project start date (ASAP scheduling)
   = hint: add 'depends:' or 'start_no_earlier_than:' to anchor scheduling logic

Rationale: In PMI/CPM methodology, every task except the project start should have at least one predecessor or date constraint to define its logical position in the schedule. Tasks without these are "dangling" or "orphan" tasks that will default to ASAP scheduling (project start date), which may be unintentional. This diagnostic helps ensure network completeness and identifies tasks that might be missing dependencies.

Note: Container tasks are not checked - only leaf tasks that represent actual work units.


E001: Circular Specialization

Severity: Error

Trigger: Profile specialization chain contains a cycle.

Condition:

profile.specializes -> ... -> profile (cycle detected)

Message Template:

error[E001]: circular specialization detected
  --> {file}:{line}
   |
   | resource_profile {profile_a} {
   |     specializes: {profile_b}
   |                  ^^^^^^^^^^ creates cycle
   | }
   |
   = cycle: {profile_a} -> {profile_b} -> ... -> {profile_a}
   = help: remove one specialization to break the cycle

Example:

error[E001]: circular specialization detected
  --> crm_migration.proj:15
   |
   | resource_profile senior_dev {
   |     specializes: lead_dev
   |                  ^^^^^^^^ creates cycle
   | }
   |
   = cycle: senior_dev -> lead_dev -> senior_dev
   = help: remove one specialization to break the cycle

E002: Profile Without Rate (Cost-Bearing)

Severity: Error (in --strict mode) / Warning (default)

Trigger: A profile has no rate, cannot inherit one, and is used in cost-bearing assignments.

Condition:

profile.rate.is_none()
  && get_inherited_rate(profile).is_none()
  && is_used_in_assignments(profile)

Important: If a profile has no rate but is never assigned, emit H002 (Unused Profile) instead. This avoids false fatal errors for placeholder profiles.

Message Template:

warning[E002]: profile '{profile_id}' has no rate defined but is assigned to tasks
  --> {file}:{line}
   |
   | resource_profile {profile_id} "{name}" {
   |     // no rate or rate_range
   | }
   |
   = note: cost calculations will be incomplete for: {task_list}
   = hint: add 'rate:' or 'rate_range:' block, or specialize from a profile with rate

I001: Project Cost Summary

Severity: Info

Trigger: Always emitted at end of successful schedule (unless --quiet).

Message Template:

info[I001]: project '{project_name}' scheduled successfully
   |
   = duration: {duration} ({start} to {end})
   = cost: ${min} - ${max} (expected: ${expected})
   = tasks: {total} ({concrete} concrete, {abstract} abstract assignments)
   = critical path: {critical_count} tasks

Example:

info[I001]: project 'CRM Migration' scheduled successfully
   |
   = duration: 89 days (2025-01-06 to 2025-05-09)
   = cost: $245,000 - $312,000 (expected: $278,500)
   = tasks: 28 (22 concrete, 6 abstract assignments)
   = critical path: 12 tasks

I002: Refinement Progress

Severity: Info

Trigger: Emitted with --verbose to show abstraction refinement status.

Message Template:

info[I002]: refinement status
   |
   = profiles defined: {profile_count}
   = profiles assigned: {assigned_count}
   = concrete assignments: {concrete_count} ({concrete_pct}%)
   = abstract assignments: {abstract_count} ({abstract_pct}%)
   = cost certainty: {certainty}%

Cost Certainty Formula:

certainty = 100 - (total_spread / total_expected * 100)

I003: Resource Utilization Summary

Severity: Info

Trigger: Emitted after successful scheduling when project has resources assigned.

Message Template:

info[I003]: Resource utilization ({start_date} - {end_date})
  {resource_id}: {percent}% ({used_days}/{total_days} days) [{status}]
  ...
  --> {file}

Status Indicators:

  • [OVER] - Utilization > 100% (over-allocated)
  • [HIGH] - Utilization > 80%
  • [LOW] - Utilization < 20% (with some assignments)
  • [IDLE] - No assignments

Example:

info[I003]: Resource utilization (2026-02-01 - 2026-03-06)
  pm: 41% (8.0/26 days)
  dev1: 231% (60.0/26 days) [OVER]
  dev2: 150% (39.0/26 days) [OVER]
  qa: 15% (4.0/26 days) [LOW]
  --> project.proj

Calculation:

utilization_percent = (used_days / (total_working_days * capacity)) * 100

Where:

  • used_days = sum of daily resource units across all assigned tasks
  • total_working_days = working days in schedule period (respects calendar)
  • capacity = resource capacity (1.0 = 100%)

CLI Integration

Default Output

$ utf8proj schedule project.proj

warning[W001]: task 'api_development' is assigned to abstract profile 'backend_developer'
  --> project.proj:45
   ...

warning[W002]: task 'data_migration' has wide cost uncertainty (120% spread)
  --> project.proj:67
   ...

info[I001]: project 'CRM Migration' scheduled successfully
   = duration: 89 days (2025-01-06 to 2025-05-09)
   = cost: $245,000 - $312,000 (expected: $278,500)

Strict Mode

$ utf8proj schedule --strict project.proj

error[W001]: task 'api_development' is assigned to abstract profile 'backend_developer'
  --> project.proj:45
   ...

error: aborting due to 1 previous error

Quiet Mode

$ utf8proj schedule --quiet project.proj
# No output unless errors

JSON Output (for tooling)

$ utf8proj schedule --format=json project.proj
{
  "diagnostics": [
    {
      "code": "W001",
      "severity": "warning",
      "message": "task 'api_development' is assigned to abstract profile 'backend_developer'",
      "file": "project.proj",
      "line": 45,
      "column": 10,
      "spans": [
        {"start": 44, "end": 62, "label": "abstract profile, not a concrete resource"}
      ],
      "notes": ["cost range is $4,000 - $8,000 (100% spread)"],
      "hints": ["assign a concrete resource to lock in exact cost"]
    }
  ],
  "schedule": { ... }
}

Implementation Notes

Diagnostic Struct

pub struct Diagnostic {
    pub code: DiagnosticCode,
    pub severity: Severity,
    pub message: String,
    pub file: Option<PathBuf>,
    pub line: Option<usize>,
    pub column: Option<usize>,
    pub spans: Vec<Span>,
    pub notes: Vec<String>,
    pub hints: Vec<String>,
}

pub enum Severity {
    Error,
    Warning,
    Hint,
    Info,
}

pub enum DiagnosticCode {
    // Structural Errors
    E001, // Circular specialization
    E002, // Profile without rate
    E003, // Infeasible constraint

    // Warnings
    W001, // Abstract assignment
    W002, // Wide cost range
    W003, // Unknown trait
    W004, // Approximate leveling
    W005, // Constraint zero slack
    W014, // Container dependency without child dependencies

    // Hints
    H001, // Mixed abstraction
    H002, // Unused profile
    H003, // Unused trait
    H004, // Task without scheduling constraint

    // Info
    I001, // Project cost summary
    I002, // Refinement progress
    I003, // Resource utilization
    I004, // Project status
    I005, // Earned value summary

    // Calendar Errors
    C001, // Zero working hours
    C002, // No working days

    // Calendar Warnings
    C010, // Task on non-working day
    C011, // Calendar mismatch (project vs resource)

    // Calendar Hints
    C020, // Low availability (<50%)
    C022, // Suspicious hours (>16h/day or 7-day week)
    C023, // Redundant holiday
}

Emitter Trait

pub trait DiagnosticEmitter {
    fn emit(&mut self, diagnostic: &Diagnostic);
    fn has_errors(&self) -> bool;
    fn error_count(&self) -> usize;
    fn warning_count(&self) -> usize;
}

Built-in Emitters

  • TerminalEmitter - Colored output for CLI
  • JsonEmitter - Machine-readable JSON
  • LspEmitter - LSP diagnostic format (future)

Calendar Diagnostics (C001-C023)

Calendar diagnostics help identify configuration issues with working calendars that may affect scheduling. Use --calendars flag to filter and show only calendar diagnostics.

C001: Zero Working Hours

Severity: Error

Trigger: A calendar has no working hours defined.

Message Template:

error[C001]: calendar '{calendar_id}' has no working hours defined
  --> {file}
   = hint: add 'working_hours:' to define when work can occur

C002: No Working Days

Severity: Error

Trigger: A calendar has no working days defined.

Message Template:

error[C002]: calendar '{calendar_id}' has no working days defined
  --> {file}
   = hint: add 'working_days:' (e.g., mon-fri)

C010: Task Scheduled on Non-Working Day

Severity: Warning

Trigger: A task is scheduled to start on a day that is not a working day according to the project calendar.

Message Template:

warning[C010]: task '{task_id}' scheduled to start on {date} ({day_name}), which is a non-working day
  --> {file}
   = hint: adjust task constraints or calendar

C011: Calendar Mismatch

Severity: Warning

Trigger: A resource is assigned to a task but uses a different calendar than the project.

Message Template:

warning[C011]: task '{task_id}' uses project calendar '{project_cal}' but assigned resource '{resource_id}' uses calendar '{resource_cal}'
  --> {file}
   = note: different calendars may cause scheduling conflicts
   = hint: ensure project and resource calendars are compatible

C020: Low Availability Calendar

Severity: Hint

Trigger: A calendar has less than 50% availability (fewer than 3 working days per week).

Message Template:

hint[C020]: calendar '{calendar_id}' has only {days} working day(s) per week (<50% availability)
  --> {file}
   = note: low availability may significantly extend schedule duration

C022: Suspicious Working Hours

Severity: Hint

Trigger: A calendar has more than 16 hours per day, OR has 7 working days per week with 8+ hours per day.

Message Template (excessive hours):

hint[C022]: calendar '{calendar_id}' has {hours} hours/day which may be unrealistic
  --> {file}
   = hint: typical work day is 8 hours

Message Template (7-day week):

hint[C022]: calendar '{calendar_id}' has 7-day workweek with {hours} hours/day
  --> {file}
   = note: verify this is intentional (e.g., 24/7 operations)

C023: Redundant Holiday

Severity: Hint

Trigger: A holiday is defined on a day that is already a non-working day (e.g., Sunday holiday when Sunday is not a working day).

Message Template:

hint[C023]: holiday '{holiday_name}' on {date} falls on {day_name}, which is already a non-working day
  --> {file}
   = note: this holiday has no scheduling impact

CLI Calendar Flag

Use --calendars with check or schedule commands to show only calendar-related diagnostics:

# Show only calendar diagnostics
utf8proj check project.proj --calendars

# Combined with other flags
utf8proj schedule project.proj --calendars --strict

Future Diagnostics (Not Yet Specified)

These may be added in future versions:

  • W006: Deadline at risk (critical path exceeds constraint)
  • W007: Resource over-committed across projects
  • H005: Task with no assignments
  • H006: Redundant dependency (transitive)
  • C021: Missing common holiday (planned but not implemented)